Location/Limits | Grosenbacher Road at Unnamed Tributary 15 to Potranca Creek. |
Project Start Date | 2022 |
Anticipated Completion | Q4 2025 |
Status | Design 30% |
Project Description
This project will replace existing 30” corrugated metal pipe with a structure capable of passing the 1% storm event. This project may also include channel improvements and USACE permitting.
Project Budget
$4,025,000
Additional Information
Consultant
Maestas & Associates LLC
Advertise Date
TBD
Contractor
TBD
Construction Cost
$ 3,000,000
Construction Start Date
TBD
Construction End Date
TBD
Joint Bid
TBD
Project Manager